Scottsdale unanimously approves $300 million ASM semiconductor headquarters, 500 jobs
SCOTTSDALE, ARIZONA — September 17, 2024

Scottsdale unanimously approves $300 million ASM semiconductor headquarters, 500 jobs

Scottsdale City Council unanimously approved a development agreement with advanced semiconductor materials company ASM to establish their North American headquarters, bringing 500 high-wage tech jobs, $300 million investment, and major sustainability commitments.


Scottsdale Seals $300 Million ASM Semiconductor Headquarters Deal in Unanimous Vote; Brings 500 High-Wage Jobs and Strategic Water Asset

On September 17, 2024, the Scottsdale City Council unanimously adopted Resolution 13158, green-lighting a development agreement with Advanced Semiconductor Materials (ASM) to establish the company's North American headquarters and largest innovation center on 21 acres south Loop 202. The vote was not a formality—it capped nearly a year of staff coordination and deal refinement, according to council members, and landed on an agreement so thoroughly vetted that council members openly marveled at the alignment between public and private interests.

ASM, a 56-year-old Dutch-founded equipment supplier to chipmakers Intel and TSMC, will invest over $300 million in a 400,000-square-foot R&D facility, relocate 500 net-new positions from Phoenix to Scottsdale (700 existing jobs are also relocating), and deliver 600 acre-feet of renewable water—195+ million gallons—to the city. The direct economic impact to Scottsdale is estimated at $8 million over ten years; with indirect effects included, the figure exceeds $14 billion regionally.

The deal required no rezoning; ASM's operations fit existing industrial (I-1) zoning. Instead, the council approved a performance-based infrastructure reimbursement agreement capped at $6,351,659.84, contingent on ASM building a $55 million payroll by year six and constructing required public roadway segments and utility infrastructure.

Key Speeches

"This new headquarters really does serve as a magnet for top talent. It diversifies our industry base, which is a huge focus of our economic development strategic plan to make sure that we are active in emerging technology and emerging technologies." — Terry Kilgore, Economic Development Director

"We supply deposition equipment to leading semiconductor manufacturers like the Intels and TSMCs of the world. We design and develop equipment in a true R&D setting, develop tools, make sure they meet customer specifications and customer requirements, and then we ship those tools to customer sites and work with them to qualify it into their production flows." — Steve Ryder, ASM Corporate Vice President

"As a former chemist and a former chemistry teacher, I am so appreciative that you will be working with SSD to support our STEM projects. I think we all know when you major in science you put in a whole lot of time in that lab, but to know that these opportunities exist at the end of that curriculum is really tremendous for our school system, for our students, for keeping our families here." — Councilwoman Jan Dubauskas

"This is such a good place to do business, such a good place to live. The company has been very proactive working with your neighbors, with me, with others on council to address some design issues—some pretty significant ones. That is the kind of cooperation that really helps make these projects move smoothly." — Councilwoman Solange Whitehead

Timeline

Opposition

None recorded. No speakers against the project.

Support

Project Details

Vote Breakdown

Individual votes not stated in transcript, but voice vote was clearly unanimous.

Outcome & Next Steps

The council adopted Resolution 13158 unanimously. ASM clears the infrastructure agreement phase and proceeds to the Design Review Board hearing on October 3, 2024, at which time site-specific design, landscape, architectural, and coordination issues with the neighboring Optima development will be adjudicated. David Hovy Jr., president of Optima, flagged concerns about garage proximity and elevation changes in his public comments and indicated that detailed renderings of ASM's revised proposal would be helpful during ongoing negotiations. Both Hovy and Solange Whitehead indicated confidence that design issues would be resolved cooperatively; no conditions were imposed by the council on the resolution beyond the infrastructure and performance provisions already embedded in the agreement.

ASM will also pursue formal development approvals through the city's design-review process, though no rezoning is required.

Controversies & Context

The most significant unresolved issue is design coordination between ASM's facility and the adjacent Optima condominium project. David Hovy Jr. indicated that the garage location, elevation changes, tree sizes, and bicycle path alignments are under active negotiation and critical to financing Optima's second condominium building. However, Hovy's tone was constructive; he explicitly praised ASM's willingness to engage and characterized the projects as compatible. Council members Solange Whitehead and Jan Dubauskas also noted ASM's proactive cooperation on design matters and predicted smooth resolution at the DRB stage.

No other controversies were raised. The deal was presented as a consensus outcome of months of staff refinement and coordination. Mayor Ortega's closing remarks alluded to the historical role of State Trust Land proceeds in Arizona's education system, anchoring the project in a longer narrative of public benefit.

One notable procedural detail: Terry Kilgore, the presenting Economic Development Director, is in her new role at the city, and council members explicitly congratulated her on inheriting such a high-profile project.

Duration

Other Notable Items

No other substantive agenda items were debated. The council approved five consent-agenda items (routine approvals) in a unanimous voice vote. A Hispanic Heritage Month proclamation was read and city employees were recognized.

═════════════════════════════════════════════════════════════════