Apache Junction secures 4,741 acre-feet Verdie River allocation, supports 4,000 homes by 2034
Apache Junction Water District board approved continuation of long-range Verdie River dam project after successfully negotiating water allocation against larger competing cities, while addressing multiple concurrent infrastructure expansions and monitoring unresolved Colorado River interstate water disputes.
Apache Junction Water District Locks in Verdie River Dam Allocation Amid Colorado River Uncertainty
The Apache Junction Water District board met on February 17th, 2026, to hear a critical update on the Bartlett Dam feasibility study—a multi-year, multi-billion-dollar water infrastructure project that hinges on the district's ability to maintain a secure long-term allocation despite competition from larger Arizona cities and federal intervention. The director's report revealed that a coalition of 10–11 smaller cities, led by Apache Junction, successfully defeated a rival faction of eight larger cities in negotiations over how to divide the dam's water supply after the federal government unexpectedly demanded 50% of the project's capacity. The smaller cities prevailed, maintaining their original 4,741 acre-feet allocation—equivalent to approximately 1,500 acre-feet annually and sufficient to serve roughly 4,000 new homes. Concurrently, the board learned that upper and lower Colorado River basin states failed to reach consensus on water reallocation by a February 13th deadline, leaving the federal government to determine future water distribution under a framework dating to the 1920s Colorado River Compact.
Timeline
-
Director's presentation (Mike): Updated board on Verdie River/Bartlett Dam feasibility study launched in 2023; federal request for 50% of dam water prompted reallocation negotiations among SRP partner cities; smaller-cities coalition voted 10–11 to 8 to maintain original water allocation methodology.
-
Water allocation outcome: Apache Junction's allocation confirmed at 4,741 acre-feet total (1,500 acre-feet annually); federal government contribution estimated at $500 million against total project cost of $3.4 billion; feasibility study on track through mid-2027; design phase to follow; congressional approval targeted for 2029; dam completion projected 2034.
-
Federal government posture: Remains a partner and funding source despite initial heavy-handed 50% demand; board pressed on whether federal requirement for 50% reflected genuine need or arbitrary appetite; director clarified federal government is not opposed but requiring environmental review and economic justification.
-
Colorado River interstate dispute: Lower basin states reached internal agreement; upper basin states could not; February 13th deadline passed without resolution; issue now federal government responsibility; Arizona faces disproportionate burden if other states continue overuse; California retains senior water rights and faces no restrictions.
-
Concurrent infrastructure: $2 million Ironwood well drilling project (north of Ray) to commence within two months; final water treatment plant buildout ($30–40 million) underway with developer partnership; Booster 2 expansion/upgrade ($4–8 million) requiring additional budget allocation for following year.
-
Budget: December 16th, 2025 special meeting minutes approved unanimously (7–0); final $180,000 payment for original feasibility study to be made next year.
Key Speeches
"Roughly in 2023, SRP put out a request to us of how many acre feet of water that we would like as be part of this dam. Uh we went big and bold at that point in time and asked for 50,000 acre feet. Um and then we went through a process with the subcommittee with SRP and we informed you guys a lot of that. Um after our meeting, we came out that uh after we separated out between all the cities, we're roughly looking at 7,413 ac." — Mike (Director)
"The federal government now came in roughly in November finally give us what they required. Well, lo and behold, they want 50% of the actual water in the dam now. So, it went back to the subcommittee to say, 'Hey, you know, how much do you guys how much how are we going to reallocate this out?'" — Mike (Director)
"Uh, 10 other cities voted with us. Just keep with our original way we separated out the allocation of water. Eight other cities did not. Well, the eight other cities were the big boys. The Ammois, the big Phoenix, everybody else that wanted to change because it helped them receive more water. Well, we actually got the little guys together and actually won something finally." — Mike (Director)
"Uh because this is damning up another waterway and then it has to show that there's not only an economic reason behind it, but environmentally doesn't impact too many things and then they are also pro a partner in this. I believe currently they're at about a half a million dollars that they will be providing as part of this project. Possibly could even provide more as we get through some of that as we build the dam that may reduce some of our costs." — Mike (Director), responding to Chip Wilson question on why congressional approval is required
"The lower states were able to get together and come up with uh their solution. The upper basin states could not come up with a solution that matched ours. Uh so now it's back in the federal government's hands and they will determine on how they reallocate the RI Colorado River. So we're going back to the old packs from 1920s." — Chip Wilson, on Colorado River interstate dispute
Project Details
-
Project name: Verdie River Sedimentation Mitigation Study / Bartlett Dam Project
-
Lead entities: SRP (Salt River Project); Apache Junction Water District; coalition of 10–11 smaller Arizona cities (including Apache Junction) versus 8 larger cities (including Phoenix and Ahwatukee)
-
Key personnel: Ryan Draper (Water Administrator, Water District Adviser) — led negotiations for smaller cities' coalition
-
Location: Verdie River (specific coordinates not provided in transcript)
-
Original allocation request (2023): 50,000 acre-feet (SRP's initial call for participation)
-
First negotiated allocation (2023–2025): 7,413 acre-feet across all participating cities
-
Federal government demand (November 2025): 50% of dam water
-
Current allocation (February 2026): 4,741 acre-feet total for Apache Junction's share of the smaller-cities allocation; equivalent to approximately 1,500 acre-feet annually (available only every third year)
-
Projected capacity to serve: Approximately 4,000 new homes (based on approximately three homes per acre-foot)
-
Project timeline:
- Feasibility study: 2023–mid-2027 (on schedule)
- Design phase: Mid-2027 onward
- Congressional approval: Targeted 2029
- Dam completion: 2034
-
Total estimated project cost: $3.4 billion
-
Federal government contribution: Approximately $500 million (subject to increase as environmental and design phases proceed)
-
District's current financial commitment: Roughly $500,000 spent to date; final payment of $180,000 scheduled for following year (completing original feasibility-study funding)
Opposition & Controversy
Eight larger Arizona cities opposed maintaining the smaller cities' original water allocation methodology:
-
Cities opposing (primary concern): Phoenix, Ahwatukee, and six others totaling eight larger municipalities
-
Their argument: The 50% federal government demand necessitated a complete reallocation of the water supply; smaller cities' original allocation formulas no longer worked under the new constraints and should be recalculated to provide larger cities with greater access
-
Outcome: The smaller-cities coalition (10–11 cities) outvoted them in the SRP subcommittee and reaffirmed the original allocation based on each city's quantified need rather than wants
-
Underlying tension: Director Mike characterized the larger cities' position as self-interested ("helped them receive more water"), while the smaller cities' strategy was to ensure that even marginal partners would receive some allocation sufficient to keep them invested in the project's regional benefits
Support
The smaller cities' coalition (10–11 municipalities including Apache Junction) prevailed:
-
Coalition argument: Original allocation methodology (based on stated need rather than want) should be preserved; smaller allocations to marginal partners keep those cities engaged and preserve regional benefits of the project; cutting out smaller partners would fragment the coalition's political and practical leverage
-
Federal government posture: While demanding 50% of water, federal government remains a committed funding partner ($500 million) and is not opposed to the project; federal requirement for congressional approval and environmental/economic justification is standard procedure for major water infrastructure, not hostile intervention
Vote Breakdown
-
Allocation vote (smaller cities vs. larger cities in SRP subcommittee): 10–11 to 8 (smaller cities prevailed; allocation maintained at 4,741 acre-feet for Apache Junction's share)
-
December 16th, 2025 special meeting minutes approval: 7–0 (unanimously passed)
-
Individual vote breakdown not stated in transcript for the allocation vote. The director reported that the coalition of smaller cities voted as a bloc and succeeded 10–11 to 8; this vote occurred in the SRP subcommittee, not the Apache Junction Water District board itself. The board's explicit formal action on the allocation issue is not recorded in this transcript.
Outcome & Next Steps
The Apache Junction Water District confirmed continuation of the Verdie River/Bartlett Dam feasibility study under the negotiated allocation of 4,741 acre-feet (1,500 annually). The smaller-cities coalition's victory means Apache Junction's water supply expansion for future growth remains on track. The project is currently on schedule through mid-2027 for feasibility studies, with design to follow, congressional approval targeted for 2029, and dam completion projected for 2034.
The federal government's role has shifted from optional partner to arbiter: after the upper and lower Colorado River basin states failed to reach consensus on water reallocation by the February 13th deadline, the federal government is now tasked with determining how the seven Colorado River states will allocate water under a framework reverting to the 1920s Colorado River Compact. This outcome introduces uncertainty for Apache Junction and Arizona generally, as the federal government's eventual ruling could affect the state's overall water security and, indirectly, the viability of projects like the Verdie River dam.
The board will receive updates as new information emerges from SRP and federal government sources. The final $180,000 payment for the original feasibility study will be budgeted for the following fiscal year.
Concurrent Infrastructure Projects
The director's report included updates on three additional water infrastructure initiatives:
-
Ironwood Well Drilling ($2 million): Located north of Ray, this new well is scheduled to commence drilling within the next two months. The board anticipated that the community will see a well rig on-site as the project progresses.
-
Water Treatment Plant Final Buildout ($30–40 million): The district is partnering with a developer to complete the final construction phase of the water treatment plant, designed to support the district's production capacity needs. No timeline or developer name was specified in the transcript.
-
Booster 2 Expansion and Upgrade ($4–8 million): The district is simultaneously expanding and upgrading the Booster 2 facility. The board previously approved approximately $2 million for this project; additional budget allocation will be requested for the following year to complete the work.
Controversies & Context
The Federal Government's 50% Demand
In November 2025, the federal government unexpectedly demanded that 50% of the Verdie River dam's water be allocated to federal uses or other priorities, a dramatic reversal from the 2023–2025 negotiation process that had produced a stable allocation framework. The director characterized this as a shift from articulated federal needs to a blanket percentage demand. Chip Wilson asked why the federal demand should be accepted, Director Mike responded by explaining the federal approval process: congressional authorization requires demonstrating both economic justification and minimal environmental impact. The federal government is contributing approximately $500 million toward the $3.4 billion project cost, giving it leverage and legitimacy as a partner. However, the director noted that the district pushed back, asking the federal government to substantiate its 50% claim with documented need rather than accepting an arbitrary percentage. This ongoing negotiation remains unresolved and is "internal information at this time," according to Mike.
The Colorado River Interstate Dispute
The board's discussion revealed a broader crisis in interstate water allocation. The lower basin states (California, Nevada, Utah, Arizona) reached an internal agreement on water reallocation, but the upper basin states (Colorado, Wyoming, New Mexico, Utah) could not arrive at a matching proposal. With the February 13th deadline missed, the issue has reverted to the federal government, which will determine how to allocate Colorado River water under the 1920s Colorado River Compact—a framework that predates modern water demands and climate change impacts.
Chip Wilson expressed concern that this outcome places a disproportionate burden on Arizona because California retains senior water rights under the 1922 compact and faces no restrictions, while Arizona, as a later entrant, must bear the burden of cutbacks if overuse continues. The director acknowledged that the seven-state Colorado River system faces a tragedy-of-the-commons scenario: if states continue overusing, "there won't be any water for anybody in the end." The federal government's ultimate decision could materially affect Apache Junction's long-term water security, particularly if Arizona's overall Colorado River allocation is reduced.
Political Leverage of the Smaller Cities
The director's framing of the allocation vote as a victory for "the little guys" reveals the political and practical tension in multi-city water infrastructure projects. Larger cities with higher growth projections and political clout (Phoenix, Ahwatukee) sought to recalculate allocations in their favor under the pretext of the federal government's new 50% demand. The smaller cities, including Apache Junction, recognized that accepting a complete reallocation would disadvantage them and risk fragmenting the coalition. By maintaining the original allocation methodology based on need, the smaller cities ensured that even marginal partners would receive something—a strategy that preserved regional unity and may have strengthened the coalition's negotiating position with the federal government and SRP.
Duration
-
This item (Verdie River dam and Colorado River update): Approximately 15–20 minutes (transcript estimate)
-
Total meeting: Approximately 25–30 minutes (brief meeting with no public comment and limited discussion)
Other Notable Items
Minutes Approval: The board unanimously approved the December 16th, 2025 special meeting minutes (7–0). No substantive issues were raised.
Treasurer's Report: Mentioned but no details provided in the transcript; meeting adjourned immediately following the director's report.
View source transcript ▼
Source: Apache Junction Water District Meeting - 02/17/26 — February 18, 2026. Auto-generated YouTube transcript; may contain transcription errors.
Okay, I would like to call the Apache Junction Water District meeting for February 17th, 2026 to order and request that all cell phones be placed into the silent mo mode. Roll call. Chairperson Wilson here. Vice Chairperson Schroeder here. Board member Cross here. Board member Hec here. Board member Johnson here. Board member Nesser present. Board member Sarer here. You have a quorum, your honor. Thank you.
Uh, can I add a excuse me approval for a minutes of the December 16th, 2025 special meeting? Mr. Chair, yes. So moved. Second. Moved and seconded. Roll call. Board member Ser. Yes. Vice Chairperson Schroeder. Yes. Board member Nesser. Yes. Board member Cross. Yes. Board member Hec. Yes. Board member Johnson. Yes. And chairperson Wilson. Yes. Motion passes unanimously. All right. District manager report. Bryant. No report, your honor. Okay. District director's report. Mike. I got it. Yeah.
Good evening, Chairman Wilson and members of the board. Give me a quick second here. Do you know which drive is Rob? Do you know which drive they usually put their presentation on? It's in work. Work session or I'm sorry. It's in council meetings underwater. Should be a fighting map right now. It's in council meeting drive. Mike for work session. Council me December 16th. December 16. Those are just a meeting minutes for December that you guys just approved. Oh, there we go.
So, now we're on to director's report. All right. Uh, just want to give you guys a quick update on the Verie River sedimentation mitigation study update. So, our Verdie or the Bartlett Dam that we've been working on for the last, believe it or not, almost four years now. Um, kind of give you a little background before I get into this. Uh roughly in 2023, SRP put out a request to us of how many acre feet of water that we would like as be part of this dam.
Uh we went big and bold at that point in time and asked for 50,000 acre feet. Um and then we went through a process with the subcommittee with SRP and we informed you guys a lot of that. Um after our meeting, we came out that uh after we separated out between all the cities, we're roughly looking at 7,413 ac. So big dramatic drop, but we're still getting a a part of that bucket. So time continued on.
We're still part of the study, working with our other uh cities and working through the process with SRP and the federal government doing EPA study so we can continue build this dam. And the federal government now came in roughly in November finally give us what they required. Well, lo and behold, they want 50% of the actual water in the dam now.
So, it went back to the subcommittee to say, "Hey, you know, how much do you guys how much how are we going to reallocate this out?" Uh, we had a big push here recently. Uh, Ryan Draper, our water administrator, our water district adviser, went to the board meeting and most cities wanted to go back to the way we allocated out originally when we received the 7,413 acre feet.
Some other cities like, "Well, no, we need to redo this whole thing because it just doesn't work for us anymore." So SRP had two different options. Uh we actually went and discussed this uh ahead of time with the subcommittee, worked through the process. Um we end up going back to our original uh allocations on how we did it by your needs rather than just what your wants were. So we worked through that process. Uh 10 other cities voted with us.
Just keep with our original way we separated out the allocation of water. Eight other cities did not. Well, the eight eight other cities were the big boys. The Ammois, the big Phoenix, everybody else that wanted to change because it helped them receive more water. Well, we actually got the little guys together and actually won something finally. So, we worked through that process. Our alloc allocation will stay the same at this 4,741 acre feet of capacity.
So, we're a little bit less than half of what we originally planned out there or what we originally negotiated. We are still requesting that the federal government give us their requirements, what they need, not just I want half of your supply of what you're building out of this dam. Show us your need. What do you have to back up if cap supplies go down or if other things happen throughout the water system? So, we're working through that process with them also.
Uh, so this isn't the end of all of our negotiations on how much water we'll receive, but right now we're roughly about 4,41 acre feet, but remember this is only available every third year. So it's really only 1500 acre feet. So roughly that you get about three homes per acre foot. So we're looking at roughly about 4,000 new homes that we could provide water service to with this or back up our existing supplies. So just kind of give you guys an idea. Any questions on that?
So far, Mike, how recent is this information? I mean, this just came out last Thursday, Wednesday, Thursday. We we voted on this. So, this is all new. There's some additional information. That's all internal information at this time, but this is kind of where we're at that can provide to you guys at this point. And how close was the vote and how many smaller cities and towns? I think it was it was either 10 10 or 11 to eight. Okay.
So a lot of the small like I said a lot of the smaller cities joined in with us when we initially talked about it uh back three years ago uh some of the cities were such a small allocation we all looked at each other and said how much water is needed to keep you in this as a partner so that the whole region benefits from this and everybody came up with this number of 4500 acre feet so roughly 1500 acre feet per year.
So that kept about five or six partners in because they were at least going to get something out of their process as they got to the end rather than being cut out of the whole supply because they couldn't show the need that they wanted. So kind of give you an update. Uh we did have a meeting we approved still the budget hasn't changed. We're still on budget from our last meeting that we had here.
Uh we have one more payment I believe $180,000 next year and that'll be our final payment for this the original feasibility study that we're going through uh with SRP. So as you can see here uh we roughly started in 2023. We're moving through the feasibility study. Um they got to balance it versus the environmental impacts and they're working through this. So we're right here in 2026 still on schedule.
probably won't done be done till mid 2027 and then start on our actual design and then possibly congressional approval in 2029 with a dam not being completed till like 2034. So again, this is long range planning for water supplies here, but just want to kind of keep you guys in the loop a loop where we are at in the process. So a lot of things happening out there. Mr. Chair, yes. Hey Mike, why does it require congressional approval?
Uh because this is damning up another waterway and then it has to show that there's not only an economic reason behind it, but environmentally doesn't impact too many things and then they are also pro a partner in this. I believe currently they're at about a half a million dollars that they will be providing as part of this project. Possibly could even provide more as we get through some of that as we build the dam that may reduce some of our costs. So, so they're not opposed to us.
Half a billion. You said half a million or billion? Billion. Oh, half a billion. Billion. Oh, it sounded like half a million from up here. 500,000 into this and they're telling us what to do. No. Okay. No, we're roughly a half a million into it ourselves here at the district. That I understand. Yes. Okay. Well, we'll be working through that. In the end, I think the last estimate they were at is roughly about a $3.4 billion job in the end.
So again, huge, huge, huge deal here in Arizona to work through this. So government is part of that. They we have to get all the approvals through them. Any questions on the verdy system? I'll keep you guys updated as new news comes up. We'll be working through obviously some of these. We're not involved. This is just going on behind the scenes with SRP on the feasibility studies. Uh we just only get told when the bill goes up or down or if we're on track and on time right now. Okay.
Uh just some random updates throughout the system. Uh you guys approved a $2 million well drilling uh this year. So on Ironwood just north of Ray, uh if you see a well rig out there, we'll be drilling that new well here in the next two months. You'll see a well rig out there next to that community. You guys will be seeing that. We also started on the final buildout of our water treatment plant.
Roughly another 30 to40 million dollar job that we're working on with the developer to help supply their production they need for their system. And then at booster 2 we're expanding that and then upgrading it at the same time. So roughly about 4 to 8 million job that we're working through that process right now. We started out with approval of roughly about I think it was $2 million earlier this year. So we'll be putting some more money in the budget for next year to finish that project.
But just quick update from the system. Any questions? Anything else? Mayor, real quick, since uh the states couldn't get along, upper and lower basin, where are we at now? Yes. Uh the the lower states were able to get together and come up with uh their solution. The upper basin states could not come up with a solution that matched ours. Uh so now it's back in the federal government's hands and they will determine on how they reallocate the RI Colorado River.
So we're going back to the old packs from 1920s. Uh they're going to be looking through those. Uh there's a lot of negotiation going on. Uh reading back through a lot of that. So uh hopefully there there's not a new deadline. They had the deadline I believe it was February 13th to have a solution and that has passed and nothing was resolved.
So, uh, it really stays as is, as it's been in the past, but that's not the best scenario for anybody in the seven states that receives Colorado River because if people keep overusing, there won't be any water for anybody in the end.
So hopefully the federal government makes everybody sit down at the table again and says, "Okay, how can we cut back and not just put the burden on Arizona or on Colorado because they were late to the game back in the early days and California has senior rights and there they don't have to do any restrictions or anything." So, federal government will be working through that process.
We haven't heard much if there's a a new date that they will provide a the ultimate outcome, but I'll keep you guys informed. I won't find out some more information on that. Okay. Thank you. Thanks. Okay. Um, district treasures report. Okay, thank you. And wow, no further discussion. I will now adjourn this meeting also.